KIRANA D****A at Jakarta
17th July 2009 (Friday) 1000hrs (SIN) – 2100hrs(Jakarta) – 1 Service Engineer
Preparing tools and standby for the update from Superintendent Mr. Francis
Travel from Singapore to Jakarta and meet up with agent to hotel at 2100hrs.
Meet up Superintendent Capt. Yusra, at the hotel and discuss problem of the IGG.
18th July 2009 (Saturday) 0700hrs to 2000hrs (Jakarta) – 1 Service Engineer
Meet up the agent with Superintendent Capt. Yusra in the morning and set off to REDECO, PETROLIN UTAMA (Jakarta), where the vessel docking for discharging.
Attended the vessel and meet up with Chief Engineer, discuss with him the problem.
Replace the Output card, and run the system and found the system running satisfactory.
Adjust the cooling Jacket pressure to acceptable pressure.
Checked the Inter-lock for acceptable O2% contain to open to deck for OK.
Safety alarm switch checked found OK.
According to Chief Engineer that the demister for DWS and Scrubble are in working condition.
Explain to Chief Engineer the faulty check for the Output control card for errors.
Go through with Chief Engineer what to check before start the system and during operation.
Left vessel with the agent to hotel, and will left hotel tomorrow to airport for Singapore.